MB Western

Previous Jobs

  • Tierra Construction
    Owner: LBC Terminals
    Contract Amount: $820,198.00

    Sheet Pile Retaining Wall, LBC Terminals - A new steel sheet pile wall, complete with double channel wales, tie rods and sheet pile anchor wall was installed to allow expansion of the access road along the edge of the existing drainage ditch.

    Tierra Construction

    Tierra Construction


  • Rosiek Construction
    Owner: Corps of Engineers, Wallisville Locks & Dam
    Contract Amount: $451,425.44

    Corps of Engineers, Wallisville Locks & Dam - The project consisted of driving over 400 battered timber piling and 600 LF of vinyl sheet piling for the foundation and cut-off walls of the new gate structure. The new dam approach walls consisted of 12: thick precast concrete sheet piling supported by 18 battered concrete bearing piles.

    Rosiek Construction

    Rosiek Construction


  • Primetex Corporation
    Owner: MD Harbor
    Contract Amount: $480,508.00

    SH 2094 Water Control Structure - A steel sheet pile wall was driven across the old cooling water outfall channel. Upstream and downstream cofferdams were installed to install the decorative concrete to below the water level to complete the installation for the new residential complex.

    Primetex Corporation

    Primetex Corporation


  • Inland Construction
    Owner: USCG Galveston
    Contract Amount: $363,050.00

    USCG Galveston - After Hurricane Rita destroyed part of the existing concrete sheet pile breakwater, the broken concrete pile cap and broken sheet piling were removed from the slip. New concrete sheet pilings were driven and the new cast-in-place concrete caps were constructed to complete the repairs.

    Inland Construction

    Inland Construction


  • Raw Water Intake Structure, Earthwork and Pump Station
    Owner: Houston Area Water Corporation (City of Houston)
    Contract Amount: $4,567,632.00

    Raw Water Intake Structure for Northeast Purification Plant, Lake Houston. A 66 diameter sheet pile cell was constructed in the lake to access the lake bottom in 23 of water. A second braced rectangular sheet pile tunnel pit was installed to allow the 84 bore from 20 deeper. The 84 intake pipe was installed from the offshore intake structure to the onshore pumping station, some 550 away.

    Raw Water Intake Structure

    Earthwork and Pump Station


  • Vince Bayou Railroad Bridge Replacement
    Port Terminal Railroad Association
    Contract Amount: $427,815.00

    Railroad bridge for Port Terminal Railroad Association, Pasadena, Texas. The existing timber railroad bridge was removed and a new pile-supported pre-cast concrete bridge was constructed between an active track and active pipelines.

    Vince Bayou Railroad Bridge Replacement

    Vince Bayou Railroad Bridge Replacement


  • Agrifos Plant Pasadena, TX / New elevator structure complete with all equipment.
    Owner: Agrifos Fertilizer
    Contract Amount: $750.000.00

    Plant remained in operation while support tower was replaced and existing building demolition on top of rock silos. During shut down, 150 elevator was replaced and new rock mill was installed.

    Agrifos Plant

    Agrifos Plant


  • Repair of Wharf and Fender System @ Wharves 23, 24 & 25
    Owner: Port of Houston Authority
    (Manatts, Inc.)
    Contract Amount: $530,414.00

    After demolition of the existing timber fender system, new 78 long H-Piling are being driven and a new timber-faced steel frame fender system is being erected in sections and secured to the existing wharf. The 1800 long project is being completed in 600 phases.

    Repair of Wharf

    Repair of Wharf


  • Sims Bayou Bulkhead
    Owner: Phibro Refining, Inc.
    Contract Amount: $430,000.00

    The existing failed sheet pile bulkhead was removed and replaced with a new anchored sheet pile bulkhead, consisting of 75 ft. long H-Piling driven on a 1:1 batter, an H-Pile wale system, and 38 ft. long sheet piling. All of the work was performed from the water with a barge-mounted crane.

    Sims Bayou Bulkhead

    Sims Bayou Bulkhead


  • Installation of Raw Water Intake Manifold Lake Granbury
    Owner: AES Wolf Hollow Plant
    (TEPSCO)
    Contract Amount: $678,000.00

    Six piers were drilled into the lake bottom and three concrete pier caps were poured underwater to support the pre-fabricated intake manifold for the new power plant. Divers set the forms, placed the concrete and drilled in anchor bolts to secure the manifold, which was lowered by airbags in controlled descent.

    Lake Granbury

    Lake Granbury

Quick Contact

Name
Email
Phone
Comments
Verify  

Contact Details

Map711 Old Genoa Red Bluff Rd, Houston, TX 77034

Phone: (281) 487-5757
Fax: (281) 487-5726

Sitemap | Website Design by PD